Liverpool and Eyre Street Pump Station Project
PUBLIC NOTICE
LIVERPOOL & EYRE STREET PUMP STATION PROJECT
The existing Liverpool Street pump station is scheduled for replacement, with a new pump station to be built in Eyre Street. Council have engaged the services of Lucas Total Contract Solutions to undertake the construction of the new pump station and associated pipework - Map of works.
The on-site construction program is planned to commence in the coming weeks.
Whirley’s Car Park (located between Tasman Terrace, Eyre Street and King Street – opposite Dominos) will be used as a site compound and lay down area for the contractor to store plant and equipment and will have site fencing surrounding the area for safety. The car park will be unavailable for the duration of the project.
The contractors have been requested to ensure community amenity is maintained during the school holiday period and for the Tunarama Festival. Work restrictions, with the exception of the site compound, have been applied at the following locations and times:
a) No works within the Tasman Terrace foreshore reserve area during the period 15 December 2018 to 3 February 2019 inclusive;
b) No works within King Street, Tasman Terrace and Eyre Street, north of the junction of Eyre and Washington Streets, during the period 19 January 2019 to 3 February 2019 inclusive.
The project works are planned for completion by June 2019, weather permitting.
Road restrictions will be in place throughout the project with the public asked to take care when in this area.
Any queries in relation to the project can be directed to Council’s Manager Civil Operations, Craig Matena on 8621 2300.
Stephen Rufus
Chief Executive Officer
1 November 2018